Ridgeline
Demo
RCG-2390

Fairhaven Dental Group TI

CloseoutOn plan

Fairhaven Dental Group · 275 Winslow Street, Suite 100 · West Valley · Medical Office TI

Projected margin vs bid
+0.30pts
12.8% projected · 12.5% bid · +6,385
Project manager
J. Castellanos
Superintendent
K. Doyle
Project executive
R. Arden
Start
10 Nov 25
Substantial completion
25 Jun 26(was 19 Jun 26, +6d by CO)
Field schedule
5 days behind

Superintendent’s note · Substantial completion 24 Jun. Punch closed 31 Jul. Retention release pending the owner's final lien waiver package — 77 days outstanding.

Revised contract
$1.17M
$1.15M contract + $23k in 6 approved COs
Projected final cost
$1.02M
revised budget $1.03M
Cost variance
+$3,850
projected final cost against revised budget
Cost to date
$1.01M
99% of projected final cost
Billed to date
$1.16M
99% of contract · overbilled $1
Retention held
$77k
5% withheld by owner, reduced from 10% at 50%
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
99%
Field percent complete
98%
Schedule percent elapsed
100%

76 days past the contract completion date with $9,100 of cost still to spend.

Margin bridge

Margin in the bid1,150,000 at 12.5%143,750
+Margin on approved change orders6 approved · 22,935 sold against 20,400 of cost2,535
+Cost variance against revised budgetoverruns and savings across 12 cost codes3,850
= Projected margin12.8% of 1,172,935150,135

Largest movers

08 Openings(1,350)
21 Fire Suppression1,050
09 Finishes1,450
23 HVAC2,250

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements104,150104,15036,150104,150700104,850(700)99%97%
02 Existing Conditions36,50036,50037,05036,35070037,050(550)98%100%
03 Concrete15,6003,80019,40018,95018,950018,950450100%98%
05 Metals20,9006,70027,60027,35027,350027,350250100%100%
06 Wood & Plastics62,60062,60062,30062,10020062,300300100%97%
07 Thermal & Moisture15,60015,60015,45015,4005015,450150100%100%
08 Openings67,80067,80069,15068,55060069,150(1,350)99%100%
09 Finishes177,3009,300186,600184,450180,6004,550185,1501,45098%97%
21 Fire Suppression31,30031,30030,25030,250030,2501,050100%98%
22 Plumbing73,00073,00072,15070,9501,20072,15085098%100%
23 HVAC187,700187,700185,450184,3501,100185,4502,25099%100%
26 Electrical213,800600214,400214,700214,7000214,700(300)100%98%
Total — 12 cost codes1,006,25020,4001,026,650953,4001,013,7009,1001,022,8003,85099%98%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 18 firms under contract, 1 with an expired or expiring certificate.