RCG-2447

Redstone Self-Storage Conversion

FinishesOn plan

Redstone Storage Partners · 1155 Foundry Row · South Metro · Adaptive Reuse

Projected margin vs bid
+0.80pts
14.3% projected · 13.5% bid · +11,241
Project manager
L. Navarro
Superintendent
V. Petrov
Project executive
R. Arden
Start
26 Jan 26
Substantial completion
29 Oct 26(was 16 Oct 26, +13d by CO)
Field schedule
1 days behind

Superintendent’s note · Unit partitions complete on levels 1 and 2. Access control commissioning the week of 21 Sep. Tracking to the contract date.

Revised contract
$919k
$890k contract + $29k in 6 approved COs
Projected final cost
$787k
revised budget $795k
Cost variance
+$7,800
projected final cost against revised budget
Cost to date
$654k
83% of projected final cost
Billed to date
$793k
86% of contract · overbilled $30k
Retention held
$62k
5% withheld by owner, reduced from 10% at 50%
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
83%
Field percent complete
82%
Schedule percent elapsed
82%

50 days to substantial completion with $133,350 of cost still to spend.

Margin bridge

Margin in the bid890,000 at 13.5%120,150
+Margin on approved change orders6 approved · 28,791 sold against 25,350 of cost3,441
+Cost variance against revised budgetoverruns and savings across 15 cost codes7,800
= Projected margin14.3% of 918,791131,391

Largest movers

08 Openings(1,100)
07 Thermal & Moisture1,050
05 Metals1,600
02 Existing Conditions2,950
09 Finishes4,000

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements76,85076,85026,35064,35012,50076,85084%86%
02 Existing Conditions69,30069,30068,45064,6501,70066,3502,95097%94%
03 Concrete38,5005,15043,65043,30039,1004,20043,30035090%91%
04 Masonry15,40015,40015,15013,4001,75015,15025088%91%
05 Metals46,2006,75052,95051,35047,4003,95051,3501,60092%93%
06 Wood & Plastics15,40015,40015,35010,1005,25015,3505066%65%
07 Thermal & Moisture46,2002,30048,50047,45039,5007,95047,4501,05083%81%
08 Openings53,90053,90055,00043,35011,65055,000(1,100)79%75%
09 Finishes92,4004,65097,05095,15066,40026,65093,0504,00071%73%
21 Fire Suppression46,20046,20045,50039,4506,05045,50070087%83%
22 Plumbing30,80030,80030,90027,0503,85030,900(100)88%84%
23 HVAC46,20046,20046,65039,4507,20046,650(450)85%88%
26 Electrical107,8004,650112,450113,30097,65015,650113,300(850)86%84%
31 Earthwork23,10023,10022,95021,2501,70022,95015093%95%
32 Exterior Improvements61,6001,85063,45064,25040,95023,30064,250(800)64%61%
Total — 15 cost codes769,85025,350795,200741,100654,050133,350787,4007,80083%82%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 22 firms under contract, 1 with an expired or expiring certificate.