Ridgeline
Demo
RCG-2451

Beacon Health Medical Office TI

Rough-InBelow bid margin

Beacon Health Partners · 1420 Alder Creek Parkway, Suites 200–260 · North Metro · Medical Office TI

Projected margin vs bid
−2.03pts
9.0% projected · 11.0% bid · (68,007)
Project manager
D. Whitfield
Superintendent
M. Ferraro
Project executive
T. Hollis
Start
02 Mar 26
Substantial completion
03 Jan 27(was 18 Dec 26, +16d by CO)
Field schedule
12 days behind

Superintendent’s note · Level 2 ceiling close-up held pending resolution of CO-014. Imaging suite float fully consumed; recovery plan depends on a decision by 25 Sep.

Revised contract
$4.39M
$4.20M contract + $193k in 11 approved COs
Projected final cost
$4.00M
revised budget $3.91M
Cost variance
−$90,600
projected final cost against revised budget
Cost to date
$2.34M
59% of projected final cost
Billed to date
$2.64M
60% of contract · overbilled $73k
Retention held
$213k
5% withheld by owner, reduced from 10% at 50%
Value at risk
$110k
2 change orders built without approval

Progress

Cost percent complete
59%
Field percent complete
55%
Schedule percent elapsed
62%

116 days to substantial completion with $1,658,600 of cost still to spend.

Margin bridge

Margin in the bid4,200,000 at 11.0%462,000
+Margin on approved change orders11 approved · 193,443 sold against 170,850 of cost22,593
+Cost variance against revised budgetoverruns and savings across 12 cost codes(90,600)
= Projected margin9.0% of 4,393,443393,993

Largest movers

23 HVAC(92,550)
01 General Requirements(26,000)
02 Existing Conditions(17,000)
22 Plumbing(6,350)
21 Fire Suppression(1,150)

Open exposure

$110,408 of value at risk. 2 change orders are being built in the field without a signed change order. $98,800 of that cost is already in the forecast; none of the revenue is in the contract.

16 of 16 change orders
DescriptionSubmitted
CO-014Abandoned pneumatic tube system and non-conforming duct, L2 plenumUnforeseen ConditionWork Proceeding — Unapproved86,40096,7689d24 Jul 2647
CO-011Condensate drainage for six fan coil unitsDesign Error / OmissionSubmitted to Owner12,40013,6402d09 Jul 2662
CO-010Level 1 lobby flooring — porcelain tile in lieu of LVTOwner RequestSubmitted to Owner26,90030,93507 Aug 2633
CO-015Access panels at 14 VAV and valve locationsField CoordinationDraft7,3008,395not submitted7
CO-002Fire-rated ceiling assembly, Corridor C2 (ASI-014)Design Error / OmissionApproved24,80027,2803d04 May 2622
CO-008Two additional Level 2 sub-panels (revised panel schedule)Design Error / OmissionApproved19,70021,6703d29 Jun 2621
CO-004AHJ-required smoke dampers at six corridor penetrationsRegulatory / AHJApproved16,20017,8202d14 May 2619
CO-012Sprinkler main reroute at Level 2 imagingField CoordinationApproved9,60011,0401d31 Jul 2619
CO-005Solid surface upgrade, Level 2 nurse stationOwner RequestApproved22,60025,99004 Jun 2618
CO-006Relocate 4 in. sanitary line at imaging equipment padField CoordinationApproved8,75010,0631d21 May 2618
CO-007Badge readers and door position switches at nine openingsOwner RequestApproved31,40036,11018 Jun 2618
CO-003Slab depression at abandoned chase, Level 1Unforeseen ConditionApproved11,90013,6852d09 Apr 2615
CO-001Casework and hand sinks, Exam 214–218Owner RequestApproved18,40021,16017 Apr 2614
CO-009Mastic abatement under existing VCT, Suite 240Unforeseen ConditionApproved14,30016,4454d01 Apr 2614
CO-013Credit — delete two exam room sinks, Suite 260Owner RequestApproved(6,800)(7,820)15 Jul 2614
CO-016Additional data drops, Suites 210 and 220Owner RequestRejected5,9006,78511 Jun 2619
Total — 16 change orders309,750349,966of which 110,408 is at risk

Subcontractor insurance certificates on this job: 18 firms under contract, 1 with an expired or expiring certificate.