Ridgeline
Demo
RCG-2465

Summit Orthopedic Surgery Center TI

FinishesOn plan

Summit Orthopedic Group · 3300 Harrow Ridge Drive, Building 2 · West Valley · Medical Office TI

Projected margin vs bid
+0.40pts
11.9% projected · 11.5% bid · +28,427
Project manager
D. Whitfield
Superintendent
K. Doyle
Project executive
T. Hollis
Start
08 Dec 25
Substantial completion
16 Nov 26(was 30 Oct 26, +17d by CO)
Field schedule
3 days behind

Superintendent’s note · Ceilings closed in the OR block; terminal cleaning and air balance scheduled the week of 28 Sep. Three days behind, inside float.

Revised contract
$3.12M
$2.98M contract + $139k in 8 approved COs
Projected final cost
$2.75M
revised budget $2.76M
Cost variance
+$13,000
projected final cost against revised budget
Cost to date
$2.07M
75% of projected final cost
Billed to date
$2.40M
77% of contract · overbilled $52k
Retention held
$179k
5% withheld by owner, reduced from 10% at 50%
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
75%
Field percent complete
76%
Schedule percent elapsed
80%

68 days to substantial completion with $674,750 of cost still to spend.

Margin bridge

Margin in the bid2,980,000 at 11.5%342,700
+Margin on approved change orders8 approved · 138,777 sold against 123,350 of cost15,427
+Cost variance against revised budgetoverruns and savings across 12 cost codes13,000
= Projected margin11.9% of 3,118,777371,127

Largest movers

05 Metals(1,750)
26 Electrical(1,000)
07 Thermal & Moisture1,600
06 Wood & Plastics2,200
02 Existing Conditions2,650

Open exposure

  • No unapproved work in progress, no subcontractor billing ahead of production and all insurance certificates current.

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements273,200273,20093,000212,70060,500273,20078%77%
02 Existing Conditions95,70095,70093,05088,3004,75093,0502,65095%95%
03 Concrete41,0007,75048,75049,45044,5504,90049,450(700)90%89%
05 Metals54,70031,65086,35088,10076,30011,80088,100(1,750)87%90%
06 Wood & Plastics164,000164,000161,80086,80075,000161,8002,20054%57%
07 Thermal & Moisture41,00012,05053,05051,45039,35012,10051,4501,60076%74%
08 Openings177,600177,600177,950127,50050,450177,950(350)72%69%
09 Finishes464,60027,000491,600486,700302,400188,450490,85075062%63%
21 Fire Suppression82,0005,40087,40086,50070,05016,45086,50090081%77%
22 Plumbing191,30013,500204,800204,800164,50040,300204,80080%82%
23 HVAC491,9005,400497,300488,600398,55090,050488,6008,70082%82%
26 Electrical560,30020,600580,900576,850461,900120,000581,900(1,000)79%82%
Total — 12 cost codes2,637,300123,3502,760,6502,558,2502,072,900674,7502,747,65013,00075%76%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 18 firms under contract, 0 with an expired or expiring certificate.