Ridgeline
Demo
RCG-2470

Grayson Industrial Park — Building C

Sitework & StructureOn plan

Grayson Property Group · 6200 Tannery Road, Building C · South Metro · Light Industrial

Projected margin vs bid
−0.20pts
7.8% projected · 8.0% bid · (2,387)
Project manager
M. Boyd
Superintendent
P. Lindqvist
Project executive
T. Hollis
Start
20 Apr 26
Substantial completion
01 Apr 27(was 26 Mar 27, +6d by CO)
Field schedule
4 days ahead

Superintendent’s note · Steel topped out 26 Aug. Roof deck follows the erection sequence; slab-on-grade pours start 21 Sep. Four days ahead.

Revised contract
$5.51M
$5.40M contract + $108k in 3 approved COs
Projected final cost
$5.08M
revised budget $5.06M
Cost variance
−$14,700
projected final cost against revised budget
Cost to date
$2.35M
46% of projected final cost
Billed to date
$2.69M
49% of contract · overbilled $140k
Retention held
$269k
10% withheld by owner
Value at risk
$18k
1 change order built without approval

Progress

Cost percent complete
46%
Field percent complete
43%
Schedule percent elapsed
41%

204 days to substantial completion with $2,727,850 of cost still to spend.

Margin bridge

Margin in the bid5,400,000 at 8.0%432,000
+Margin on approved change orders3 approved · 108,063 sold against 95,750 of cost12,313
+Cost variance against revised budgetoverruns and savings across 15 cost codes(14,700)
= Projected margin7.8% of 5,508,063429,613

Largest movers

03 Concrete(21,250)
31 Earthwork(6,950)
01 General Requirements(5,250)
22 Plumbing(3,500)
06 Wood & Plastics(2,850)

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements371,700371,700126,650126,800250,150376,950(5,250)34%35%
02 Existing Conditions46,40046,40045,75031,60014,15045,75065069%70%
03 Concrete835,700835,700849,050525,050331,900856,950(21,250)61%59%
04 Masonry185,700185,700186,65091,95094,700186,650(950)49%50%
05 Metals928,600928,600927,200630,500296,700927,2001,40068%56%
06 Wood & Plastics46,40046,4005,10044,15049,250(2,850)10%5%
07 Thermal & Moisture371,400371,400364,150121,300242,850364,1507,25033%29%
08 Openings232,100232,100231,75051,350180,750232,10022%21%
09 Finishes139,30035,150174,450173,05018,700155,750174,45011%11%
21 Fire Suppression232,100232,100230,95081,800149,150230,9501,15035%33%
22 Plumbing139,300139,300134,90061,00081,800142,800(3,500)43%38%
23 HVAC185,700185,700184,50068,700115,800184,5001,20037%37%
26 Electrical464,30050,800515,100500,700182,550318,150500,70014,40036%38%
31 Earthwork464,300464,300471,250330,750140,500471,250(6,950)70%69%
32 Exterior Improvements325,0009,800334,800328,60023,450311,350334,8007%3%
Total — 15 cost codes4,968,00095,7505,063,7504,755,1502,350,6002,727,8505,078,450(14,700)46%43%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 23 firms under contract, 2 with an expired or expiring certificate.