RCG-2470
Grayson Industrial Park — Building C
Sitework & StructureOn planGrayson Property Group · 6200 Tannery Road, Building C · South Metro · Light Industrial
Projected margin vs bid
−0.20pts
7.8% projected · 8.0% bid · (2,387)
Project manager
M. Boyd
Superintendent
P. Lindqvist
Project executive
T. Hollis
Start
20 Apr 26
Substantial completion
01 Apr 27(was 26 Mar 27, +6d by CO)
Field schedule
4 days ahead
Superintendent’s note · Steel topped out 26 Aug. Roof deck follows the erection sequence; slab-on-grade pours start 21 Sep. Four days ahead.
Revised contract
$5.51M
$5.40M contract + $108k in 3 approved COs
Projected final cost
$5.08M
revised budget $5.06M
Cost variance
−$14,700
projected final cost against revised budget
Cost to date
$2.35M
46% of projected final cost
Billed to date
$2.69M
49% of contract · overbilled $140k
Retention held
$269k
10% withheld by owner
Value at risk
$18k
1 change order built without approval
Progress
- Cost percent complete
- 46%
- Field percent complete
- 43%
- Schedule percent elapsed
- 41%
204 days to substantial completion with $2,727,850 of cost still to spend.
Margin bridge
| Margin in the bid5,400,000 at 8.0% | 432,000 |
| +Margin on approved change orders3 approved · 108,063 sold against 95,750 of cost | 12,313 |
| +Cost variance against revised budgetoverruns and savings across 15 cost codes | (14,700) |
| = Projected margin7.8% of 5,508,063 | 429,613 |
Largest movers
| 03 Concrete | (21,250) |
| 31 Earthwork | (6,950) |
| 01 General Requirements | (5,250) |
| 22 Plumbing | (3,500) |
| 06 Wood & Plastics | (2,850) |
Open exposure
Cost code detail
Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment| Original budget | Approved COs | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| 01 General Requirements | 371,700 | — | 371,700 | 126,650 | 126,800 | 250,150 | 376,950 | (5,250) | 34% | 35% |
| 02 Existing Conditions | 46,400 | — | 46,400 | 45,750 | 31,600 | 14,150 | 45,750 | 650 | 69% | 70% |
| 03 Concrete | 835,700 | — | 835,700 | 849,050 | 525,050 | 331,900 | 856,950 | (21,250) | 61% | 59% |
| 04 Masonry | 185,700 | — | 185,700 | 186,650 | 91,950 | 94,700 | 186,650 | (950) | 49% | 50% |
| 05 Metals | 928,600 | — | 928,600 | 927,200 | 630,500 | 296,700 | 927,200 | 1,400 | 68% | 56% |
| 06 Wood & Plastics | 46,400 | — | 46,400 | — | 5,100 | 44,150 | 49,250 | (2,850) | 10% | 5% |
| 07 Thermal & Moisture | 371,400 | — | 371,400 | 364,150 | 121,300 | 242,850 | 364,150 | 7,250 | 33% | 29% |
| 08 Openings | 232,100 | — | 232,100 | 231,750 | 51,350 | 180,750 | 232,100 | — | 22% | 21% |
| 09 Finishes | 139,300 | 35,150 | 174,450 | 173,050 | 18,700 | 155,750 | 174,450 | — | 11% | 11% |
| 21 Fire Suppression | 232,100 | — | 232,100 | 230,950 | 81,800 | 149,150 | 230,950 | 1,150 | 35% | 33% |
| 22 Plumbing | 139,300 | — | 139,300 | 134,900 | 61,000 | 81,800 | 142,800 | (3,500) | 43% | 38% |
| 23 HVAC | 185,700 | — | 185,700 | 184,500 | 68,700 | 115,800 | 184,500 | 1,200 | 37% | 37% |
| 26 Electrical | 464,300 | 50,800 | 515,100 | 500,700 | 182,550 | 318,150 | 500,700 | 14,400 | 36% | 38% |
| 31 Earthwork | 464,300 | — | 464,300 | 471,250 | 330,750 | 140,500 | 471,250 | (6,950) | 70% | 69% |
| 32 Exterior Improvements | 325,000 | 9,800 | 334,800 | 328,600 | 23,450 | 311,350 | 334,800 | — | 7% | 3% |
| Total — 15 cost codes | 4,968,000 | 95,750 | 5,063,750 | 4,755,150 | 2,350,600 | 2,727,850 | 5,078,450 | (14,700) | 46% | 43% |
Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.
Subcontractor insurance certificates on this job: 23 firms under contract, 2 with an expired or expiring certificate.