Kestrel Logistics Warehouse Shell

Sitework & StructureOn plan

Kestrel Logistics Partners · 8800 Foundry Road, Lot 4 · South Metro · Warehouse Shell

Projected margin vs bid
+0.20pts
8.7% projected · 8.5% bid · +17,807
Project manager
L. Navarro
Superintendent
P. Lindqvist
Project executive
T. Hollis
Start
06 Jul 26
Substantial completion
14 Jun 27(was 11 Jun 27, +3d by CO)
Field schedule
9 days ahead

Superintendent’s note · Mass grading finished nine days early on a dry August. Foundations follow the erection sequence; steel released for fabrication 21 Aug.

Revised contract
$6.85M
$6.80M contract + $48k in 2 approved COs
Projected final cost
$6.25M
revised budget $6.27M
Cost variance
+$12,850
projected final cost against revised budget
Cost to date
$1.37M
22% of projected final cost
Billed to date
$1.54M
23% of contract · overbilled $46k
Retention held
$154k
10% withheld by owner
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
22%
Field percent complete
23%
Schedule percent elapsed
19%

278 days to substantial completion with $4,886,350 of cost still to spend.

Margin bridge

Margin in the bid6,800,000 at 8.5%578,000
+Margin on approved change orders2 approved · 48,257 sold against 43,300 of cost4,957
+Cost variance against revised budgetoverruns and savings across 15 cost codes12,850
= Projected margin8.7% of 6,848,257595,807

Largest movers

01 General Requirements(10,300)
09 Finishes(2,200)
22 Plumbing(1,600)
31 Earthwork1,150
03 Concrete11,650

Open exposure

  • No unapproved work in progress, no subcontractor billing ahead of production and all insurance certificates current.

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements407,200407,200134,65047,600369,900417,500(10,300)11%9%
02 Existing Conditions29,10029,10029,50015,65013,85029,500(400)53%52%
03 Concrete1,163,0001,163,0001,151,350433,500717,8501,151,35011,65038%37%
04 Masonry174,400174,400174,400174,4000%28%
05 Metals1,279,30030,7501,310,0501,295,000435,800859,2001,295,00015,05034%32%
06 Wood & Plastics58,10058,10058,10058,1000%1%
07 Thermal & Moisture523,300523,300523,300523,3000%9%
08 Openings290,700290,700290,700290,7000%2%
09 Finishes145,40012,550157,950160,1503,050157,100160,150(2,200)2%0%
21 Fire Suppression290,700290,700290,700290,7000%10%
22 Plumbing145,400145,400147,00023,900123,100147,000(1,600)16%17%
23 HVAC145,400145,400145,90024,050121,850145,900(500)16%16%
26 Electrical465,200465,200449,85071,950393,250465,20015%15%
31 Earthwork639,600639,600622,950310,600327,850638,4501,15049%45%
32 Exterior Improvements465,200465,200465,200465,2000%0%
Total — 15 cost codes6,222,00043,3006,265,3004,136,3501,366,1004,886,3506,252,45012,85022%23%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 13 firms under contract, 0 with an expired or expiring certificate.