RCG-2482
Cedar Bluff Urgent Care
Rough-InWatchCedar Bluff Health Network · 44 Quarry Bend Road · West Valley · Medical Office TI
Projected margin vs bid
−0.90pts
10.6% projected · 11.5% bid · (11,525)
Project manager
S. Okafor
Superintendent
A. Reyes
Project executive
R. Arden
Start
04 May 26
Substantial completion
06 Dec 26(was 04 Dec 26, +2d by CO)
Field schedule
6 days behind
Superintendent’s note · Six days behind on the rooftop unit set; the crane date slipped twice on landlord roof access. In-wall inspection booked 17 Sep.
Revised contract
$1.43M
$1.42M contract + $12k in 3 approved COs
Projected final cost
$1.28M
revised budget $1.27M
Cost variance
−$12,900
projected final cost against revised budget
Cost to date
$520k
41% of projected final cost
Billed to date
$601k
42% of contract · overbilled $19k
Retention held
$60k
10% withheld by owner
Value at risk
$13k
2 change orders built without approval
Progress
- Cost percent complete
- 41%
- Field percent complete
- 38%
- Schedule percent elapsed
- 59%
Cost is −19 points behind the calendar. 88 days remain to substantial completion and $759,900 of cost is still to spend.
Margin bridge
| Margin in the bid1,420,000 at 11.5% | 163,300 |
| +Margin on approved change orders3 approved · 11,925 sold against 10,550 of cost | 1,375 |
| +Cost variance against revised budgetoverruns and savings across 12 cost codes | (12,900) |
| = Projected margin10.6% of 1,431,925 | 151,775 |
Largest movers
| 07 Thermal & Moisture | (5,600) |
| 26 Electrical | (5,350) |
| 05 Metals | (3,000) |
| 23 HVAC | (2,000) |
| 22 Plumbing | 1,600 |
Open exposure
Cost code detail
Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment| Original budget | Approved COs | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| 01 General Requirements | 130,300 | — | 130,300 | 45,200 | 53,300 | 75,150 | 128,450 | 1,850 | 41% | 41% |
| 02 Existing Conditions | 45,600 | — | 45,600 | 46,500 | 35,750 | 10,750 | 46,500 | (900) | 77% | 77% |
| 03 Concrete | 19,500 | 4,150 | 23,650 | 23,450 | 15,850 | 7,600 | 23,450 | 200 | 68% | 64% |
| 05 Metals | 26,000 | — | 26,000 | 26,050 | 18,350 | 10,650 | 29,000 | (3,000) | 63% | 64% |
| 06 Wood & Plastics | 78,100 | — | 78,100 | 78,700 | 8,250 | 70,450 | 78,700 | (600) | 10% | 13% |
| 07 Thermal & Moisture | 19,500 | — | 19,500 | 19,150 | 12,150 | 12,950 | 25,100 | (5,600) | 48% | 41% |
| 08 Openings | 84,600 | — | 84,600 | 84,450 | 24,350 | 60,100 | 84,450 | 150 | 29% | 30% |
| 09 Finishes | 221,400 | 2,000 | 223,400 | 219,500 | 36,300 | 187,100 | 223,400 | — | 16% | 15% |
| 21 Fire Suppression | 39,100 | 2,200 | 41,300 | 40,550 | 17,500 | 23,050 | 40,550 | 750 | 43% | 41% |
| 22 Plumbing | 91,200 | — | 91,200 | 89,600 | 42,550 | 47,050 | 89,600 | 1,600 | 47% | 49% |
| 23 HVAC | 234,400 | 2,200 | 236,600 | 237,900 | 111,550 | 127,050 | 238,600 | (2,000) | 47% | 47% |
| 26 Electrical | 267,000 | — | 267,000 | 272,350 | 144,350 | 128,000 | 272,350 | (5,350) | 53% | 44% |
| Total — 12 cost codes | 1,256,700 | 10,550 | 1,267,250 | 1,183,400 | 520,250 | 759,900 | 1,280,150 | (12,900) | 41% | 38% |
Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.
Subcontractor insurance certificates on this job: 18 firms under contract, 1 with an expired or expiring certificate.