Cedar Bluff Urgent Care

Rough-InWatch

Cedar Bluff Health Network · 44 Quarry Bend Road · West Valley · Medical Office TI

Projected margin vs bid
−0.90pts
10.6% projected · 11.5% bid · (11,525)
Project manager
S. Okafor
Superintendent
A. Reyes
Project executive
R. Arden
Start
04 May 26
Substantial completion
06 Dec 26(was 04 Dec 26, +2d by CO)
Field schedule
6 days behind

Superintendent’s note · Six days behind on the rooftop unit set; the crane date slipped twice on landlord roof access. In-wall inspection booked 17 Sep.

Revised contract
$1.43M
$1.42M contract + $12k in 3 approved COs
Projected final cost
$1.28M
revised budget $1.27M
Cost variance
−$12,900
projected final cost against revised budget
Cost to date
$520k
41% of projected final cost
Billed to date
$601k
42% of contract · overbilled $19k
Retention held
$60k
10% withheld by owner
Value at risk
$13k
2 change orders built without approval

Progress

Cost percent complete
41%
Field percent complete
38%
Schedule percent elapsed
59%

Cost is −19 points behind the calendar. 88 days remain to substantial completion and $759,900 of cost is still to spend.

Margin bridge

Margin in the bid1,420,000 at 11.5%163,300
+Margin on approved change orders3 approved · 11,925 sold against 10,550 of cost1,375
+Cost variance against revised budgetoverruns and savings across 12 cost codes(12,900)
= Projected margin10.6% of 1,431,925151,775

Largest movers

07 Thermal & Moisture(5,600)
26 Electrical(5,350)
05 Metals(3,000)
23 HVAC(2,000)
22 Plumbing1,600

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements130,300130,30045,20053,30075,150128,4501,85041%41%
02 Existing Conditions45,60045,60046,50035,75010,75046,500(900)77%77%
03 Concrete19,5004,15023,65023,45015,8507,60023,45020068%64%
05 Metals26,00026,00026,05018,35010,65029,000(3,000)63%64%
06 Wood & Plastics78,10078,10078,7008,25070,45078,700(600)10%13%
07 Thermal & Moisture19,50019,50019,15012,15012,95025,100(5,600)48%41%
08 Openings84,60084,60084,45024,35060,10084,45015029%30%
09 Finishes221,4002,000223,400219,50036,300187,100223,40016%15%
21 Fire Suppression39,1002,20041,30040,55017,50023,05040,55075043%41%
22 Plumbing91,20091,20089,60042,55047,05089,6001,60047%49%
23 HVAC234,4002,200236,600237,900111,550127,050238,600(2,000)47%47%
26 Electrical267,000267,000272,350144,350128,000272,350(5,350)53%44%
Total — 12 cost codes1,256,70010,5501,267,2501,183,400520,250759,9001,280,150(12,900)41%38%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 18 firms under contract, 1 with an expired or expiring certificate.