Ridgeline
Demo
RCG-2482

Cedar Bluff Urgent Care

Rough-InWatch

Cedar Bluff Health Network · 44 Quarry Bend Road · West Valley · Medical Office TI

Projected margin vs bid
−0.90pts
10.6% projected · 11.5% bid · (11,525)
Project manager
S. Okafor
Superintendent
A. Reyes
Project executive
R. Arden
Start
04 May 26
Substantial completion
06 Dec 26(was 04 Dec 26, +2d by CO)
Field schedule
6 days behind

Superintendent’s note · Six days behind on the rooftop unit set; the crane date slipped twice on landlord roof access. In-wall inspection booked 17 Sep.

Revised contract
$1.43M
$1.42M contract + $12k in 3 approved COs
Projected final cost
$1.28M
revised budget $1.27M
Cost variance
−$12,900
projected final cost against revised budget
Cost to date
$520k
41% of projected final cost
Billed to date
$601k
42% of contract · overbilled $19k
Retention held
$60k
10% withheld by owner
Value at risk
$13k
2 change orders built without approval

Progress

Cost percent complete
41%
Field percent complete
38%
Schedule percent elapsed
59%

Cost is −19 points behind the calendar. 88 days remain to substantial completion and $759,900 of cost is still to spend.

Margin bridge

Margin in the bid1,420,000 at 11.5%163,300
+Margin on approved change orders3 approved · 11,925 sold against 10,550 of cost1,375
+Cost variance against revised budgetoverruns and savings across 12 cost codes(12,900)
= Projected margin10.6% of 1,431,925151,775

Largest movers

07 Thermal & Moisture(5,600)
26 Electrical(5,350)
05 Metals(3,000)
23 HVAC(2,000)
22 Plumbing1,600

Open exposure

$13,387 of value at risk. 2 change orders are being built in the field without a signed change order. $11,900 of that cost is already in the forecast; none of the revenue is in the contract.

5 of 5 change orders
DescriptionSubmitted
CO-003Relocate roof curbs to clear structureField CoordinationSubmitted to Owner5,9506,8422d17 Jun 2684
CO-005Missing roof drain overflow scuppersDesign Error / OmissionSubmitted to Owner5,9506,5452d15 Aug 2625
CO-002Duct and sprinkler main conflict above corridorField CoordinationApproved4,4005,0601d13 Jun 2644
CO-001Add access panels at valve and damper locationsField CoordinationApproved2,0002,30030 May 2626
CO-004Omitted expansion joint at slab transitionDesign Error / OmissionApproved4,1504,5651d27 Jun 2612
Total — 5 change orders22,45025,312of which 13,387 is at risk

Subcontractor insurance certificates on this job: 18 firms under contract, 1 with an expired or expiring certificate.