Ridgeline
Demo
RCG-2487

Trailhead Coffee Roasters Fit-Out

FinishesBelow bid margin

Trailhead Coffee Roasters · 118 Copper Lane, Unit B · North Metro · Retail Fit-Out

Projected margin vs bid
−16.03pts
−4.0% projected · 12.0% bid · (55,305)
Project manager
S. Okafor
Superintendent
A. Reyes
Project executive
R. Arden
Start
18 May 26
Substantial completion
15 Sep 26(was 11 Sep 26, +4d by CO)
Field schedule
21 days behind

Superintendent’s note · Twenty-one days behind. The mechanical rebuy cost four weeks and the hood inspection cannot be scheduled until the shaft enclosure is closed.

Revised contract
$360k
$340k contract + $20k in 3 approved COs
Projected final cost
$374k
revised budget $317k
Cost variance
−$57,900
projected final cost against revised budget
Cost to date
$301k
80% of projected final cost
Billed to date
$296k
82% of contract · overbilled $7k
Retention held
$30k
10% withheld by owner
Value at risk
$16k
1 change order built without approval

Progress

Cost percent complete
80%
Field percent complete
85%
Schedule percent elapsed
95%

Cost is −15 points behind the calendar. 6 days remain to substantial completion and $73,650 of cost is still to spend.

Margin bridge

Margin in the bid340,000 at 12.0%40,800
+Margin on approved change orders3 approved · 19,895 sold against 17,300 of cost2,595
+Cost variance against revised budgetoverruns and savings across 11 cost codes(57,900)
= Projected margin−4.0% of 359,895(14,505)

Largest movers

23 HVAC(26,400)
09 Finishes(17,100)
01 General Requirements(9,400)
22 Plumbing(5,050)

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements26,90026,9008,95024,35011,95036,300(9,400)67%88%
02 Existing Conditions18,00018,00017,95017,950017,95050100%100%
03 Concrete3,0003,0003,0502,8502003,050(50)93%93%
06 Wood & Plastics23,90023,90023,70017,5006,20023,70020074%73%
07 Thermal & Moisture3,0003,0003,0502,6504003,050(50)87%86%
08 Openings15,0002,90017,90017,40014,7002,70017,40050084%84%
09 Finishes71,80071,80071,30063,60025,30088,900(17,100)72%82%
21 Fire Suppression9,0009,0009,0008,1508509,00091%87%
22 Plumbing26,9004,60031,50036,55033,3003,25036,550(5,050)91%90%
23 HVAC41,90041,90057,00053,80014,50068,300(26,400)79%80%
26 Electrical59,8009,80069,60070,20061,9008,30070,200(600)88%86%
Total — 11 cost codes299,20017,300316,500318,150300,75073,650374,400(57,900)80%85%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 17 firms under contract, 0 with an expired or expiring certificate.