Ridgeline
Demo
RCG-2487

Trailhead Coffee Roasters Fit-Out

FinishesBelow bid margin

Trailhead Coffee Roasters · 118 Copper Lane, Unit B · North Metro · Retail Fit-Out

Projected margin vs bid
−16.03pts
−4.0% projected · 12.0% bid · (55,305)
Project manager
S. Okafor
Superintendent
A. Reyes
Project executive
R. Arden
Start
18 May 26
Substantial completion
15 Sep 26(was 11 Sep 26, +4d by CO)
Field schedule
21 days behind

Superintendent’s note · Twenty-one days behind. The mechanical rebuy cost four weeks and the hood inspection cannot be scheduled until the shaft enclosure is closed.

Revised contract
$360k
$340k contract + $20k in 3 approved COs
Projected final cost
$374k
revised budget $317k
Cost variance
−$57,900
projected final cost against revised budget
Cost to date
$301k
80% of projected final cost
Billed to date
$296k
82% of contract · overbilled $7k
Retention held
$30k
10% withheld by owner
Value at risk
$16k
1 change order built without approval

Progress

Cost percent complete
80%
Field percent complete
85%
Schedule percent elapsed
95%

Cost is −15 points behind the calendar. 6 days remain to substantial completion and $73,650 of cost is still to spend.

Margin bridge

Margin in the bid340,000 at 12.0%40,800
+Margin on approved change orders3 approved · 19,895 sold against 17,300 of cost2,595
+Cost variance against revised budgetoverruns and savings across 11 cost codes(57,900)
= Projected margin−4.0% of 359,895(14,505)

Largest movers

23 HVAC(26,400)
09 Finishes(17,100)
01 General Requirements(9,400)
22 Plumbing(5,050)

Open exposure

$15,904 of value at risk. 1 change order is being built in the field without a signed change order. $14,200 of that cost is already in the forecast; none of the revenue is in the contract.

5 of 5 change orders
DescriptionSubmitted
CO-003Grease exhaust shaft enclosure omitted from permit setDesign Error / OmissionWork Proceeding — Unapproved14,20015,90411d27 Jul 2644
CO-005Added mural wall blocking and lighting, seating areaOwner RequestDraft3,4003,910not submitted5
CO-001Landlord-required electrical panel relocationOwner RequestApproved9,80011,2703d11 Jun 2615
CO-002Floor sink and indirect waste at espresso barRegulatory / AHJApproved4,6005,2901d24 Jun 2614
CO-004Storefront door hardware upgrade to panic deviceRegulatory / AHJApproved2,9003,33502 Jul 2612
Total — 5 change orders34,90039,709of which 15,904 is at risk

Subcontractor insurance certificates on this job: 17 firms under contract, 0 with an expired or expiring certificate.