Ridgeline
Demo
RCG-2492

Northgate Vision Center TI

MobilizationOn plan

Northgate Vision Center · 9 Larkspur Court, Suite 4 · North Metro · Medical Office TI

Projected margin vs bid
0.00pts
13.0% projected · 13.0% bid · (277)
Project manager
J. Castellanos
Superintendent
M. Ferraro
Project executive
T. Hollis
Start
17 Aug 26
Substantial completion
22 Jan 27
Field schedule
On schedule

Superintendent’s note · Demolition complete in the exam wing. Framing starts 14 Sep. Mechanical and electrical awarded; finishes out for pricing.

Revised contract
$623k
$625k contract + -$2k in 1 approved COs
Projected final cost
$542k
revised budget $542k
Cost variance
+$0
projected final cost against revised budget
Cost to date
$35k
6% of projected final cost
Billed to date
$42k
7% of contract · overbilled $2k
Retention held
$4k
10% withheld by owner
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
6%
Field percent complete
10%
Schedule percent elapsed
15%

Cost is −8 points behind the calendar. 135 days remain to substantial completion and $507,100 of cost is still to spend.

Margin bridge

Margin in the bid625,000 at 13.0%81,250
+Margin on approved change orders1 approved · (2,127) sold against (1,850) of cost(277)
+Cost variance against revised budgetoverruns and savings across 12 cost codes0
= Projected margin13.0% of 622,87380,973

Largest movers

Every cost code is tracking within $1,000 of its revised budget.

Open exposure

  • No unapproved work in progress, no subcontractor billing ahead of production and all insurance certificates current.

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements56,35056,35018,6504,95051,70056,650(300)9%6%
02 Existing Conditions19,70019,70019,6009,20010,40019,60010047%45%
03 Concrete8,5008,5008,3002,9005,4008,30020035%33%
05 Metals11,30011,30011,0503,0008,05011,05025027%28%
06 Wood & Plastics33,80033,80033,80033,8000%1%
07 Thermal & Moisture8,5008,5008,5008,5000%6%
08 Openings36,60036,60036,60036,6000%0%
09 Finishes95,80095,80095,80095,8000%2%
21 Fire Suppression16,90016,90016,90016,9000%9%
22 Plumbing39,40039,40039,40039,4000%14%
23 HVAC101,400101,400101,400101,4000%14%
26 Electrical115,500(1,850)113,650113,90014,75099,150113,900(250)13%9%
Total — 12 cost codes543,750(1,850)541,900171,50034,800507,100541,90006%10%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 6 firms under contract, 0 with an expired or expiring certificate.