RCG-2495

Anchor Point Distribution — Phase 2

PreconstructionOn plan

Anchor Point Distribution Co. · 4501 Kiln Road · South Metro · Light Industrial

Projected margin vs bid
0.00pts
9.0% projected · 9.0% bid · 0
Project manager
L. Navarro
Superintendent
V. Petrov
Project executive
T. Hollis
Start
10 Aug 26
Substantial completion
06 Aug 27
Field schedule
On schedule

Superintendent’s note · Notice to proceed 10 Aug. Grading permit in review with the county; site mobilisation planned for 28 Sep. Sitework and demolition are under contract; the balance of the job is out for pricing.

Revised contract
$3.95M
$3.95M contract · no approved change orders
Projected final cost
$3.59M
revised budget $3.59M
Cost variance
+$0
projected final cost against revised budget
Cost to date
$105k
3% of projected final cost
Billed to date
$121k
3% of contract · overbilled $5k
Retention held
$12k
10% withheld by owner
Value at risk
$0
no unapproved work in progress

Progress

Cost percent complete
3%
Field percent complete
8%
Schedule percent elapsed
8%

331 days to substantial completion with $3,489,500 of cost still to spend.

Margin bridge

Margin in the bid3,950,000 at 9.0%355,500
+Margin on approved change orders0 approved · 0 sold against 0 of cost0
+Cost variance against revised budgetoverruns and savings across 15 cost codes0
= Projected margin9.0% of 3,950,000355,500

Largest movers

31 Earthwork(3,700)
01 General Requirements3,300

Open exposure

Cost code detail

Projected final cost = cost to date + remaining committed + uncommitted budget + unapproved change order exposure + PM forecast adjustment
Original budgetApproved COs
01 General Requirements268,600268,60091,7504,650260,650265,3003,3002%0%
02 Existing Conditions33,60033,60033,2008,95024,25033,20040027%26%
03 Concrete604,700604,700604,700604,7000%13%
04 Masonry134,400134,400134,400134,4000%5%
05 Metals671,900671,900671,900671,9000%13%
06 Wood & Plastics33,60033,60033,60033,6000%0%
07 Thermal & Moisture268,700268,700268,700268,7000%0%
08 Openings168,000168,000168,000168,0000%1%
09 Finishes100,800100,800100,800100,8000%1%
21 Fire Suppression168,000168,000168,000168,0000%4%
22 Plumbing100,800100,800100,800100,8000%5%
23 HVAC134,400134,400134,400134,4000%1%
26 Electrical335,900335,900335,900335,9000%0%
31 Earthwork335,900335,900339,60091,400248,200339,600(3,700)27%22%
32 Exterior Improvements235,200235,200235,200235,2000%0%
Total — 15 cost codes3,594,50003,594,500464,550105,0003,489,5003,594,50003%8%

Rows expand to the subcontracts, purchase orders and invoices behind the committed and actual figures. Committed on every line is the sum of the commitments listed inside it; actual is the sum of the invoices and direct costs booked against it.

Subcontractor insurance certificates on this job: 4 firms under contract, 1 with an expired or expiring certificate.